2008-2009 Water Main Construction
Week 1 Dec 8-12
Pipe, fittings and equipment arrive Dec 8.
Street Breaking Dec 11.
A slow start around a gas line but a smooth 3 quarter block then.
Dec 12 crossing Jane Ave.
A smooth run then after finding and repairing the Jane Ave pipe branch.
Week 2 Dec 15-19 & Week 3 Jan 5-9
Week 4 Jan 12-16, Week 5 Jan 19-23, Week 7 Jan 26, Week 8 Mar 2-6 till present.