2.0 Project Estimate
For
this part of the document, estimations for cost, effort
and duration will be calculated using 2 different estimation
techniques, which will be elaborated in the appropriate
section.
|
|
2.1 Historical Data Used For Estimates
From the historical data for past projects, we obtained
the following cost information which shall be use in this
project's cost estimation.
Average
productivity for systems of this type: 600
LOC / person-month
Labour rate : RM 4,500 / month
|
|
Return
to top |
|
2.2 Estimation Techniques Applied And Results
Two
estimation techniques have been used to generate two independent
results for comparison purposes which will provide a more
accurate result.
>>
Process
- based
>> Lines of Code ( LOC ) - COCOMO Model
|
|
Return
to top |
|
2.2.1
Process-Based Estimation
For process-based estimation, the process is decomposed
into a relatively small set of activities or tasks. Then,
the effort required to accomplish each task is estimated.
Based on the project scope, the following software functions
are defined:
|
|
Login |
LI |
Customer
Details Management |
CDM |
Application
Processing |
AP |
Approved
Loan Management |
ALM |
Transaction
Processing |
TP |
Month-End
Interest Calculation |
MEIC |
Report
Generation |
RG |
User
Maintenance |
UM |
Logout |
LO |
|
|
Estimates
of effort ( in person – month ) for each activity
based on past projects are as below :
|
|
Process
– Based Estimation Table :
|
|
Activity
-----> |
Cust.
Comm. |
Planning |
Risk
Analysis |
Engineering |
Construction
Release |
Cust.
Eval. |
Total |
Task
-----> |
|
|
|
Analysis |
Design |
Code
|
Test
|
|
|
|
|
|
|
|
|
|
|
|
|
Function
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
LI |
0.07 |
0.07 |
0.01 |
0.02 |
0.04 |
0.05 |
0.07 |
0.05 |
0.38 |
CDM |
0.60 |
0.30 |
0.05 |
0.10 |
0.25 |
0.30 |
0.55 |
0.20 |
2.35 |
AP |
0.70 |
0.40 |
0.05 |
0.20 |
0.30 |
0.30 |
0.70 |
0.25 |
2.90 |
ALM |
0.55 |
0.35 |
0.05
|
0.15 |
0.15 |
0.20
|
0.55 |
0.25 |
2.25 |
TP |
0.60 |
0.40 |
0.05 |
0.25 |
0.30 |
0.30 |
0.65
|
0.40 |
2.95 |
MEIC |
0.70 |
0.20 |
0.10 |
0.20 |
0.25 |
0.20 |
0.70
|
0.35 |
2.70 |
RG |
0.70 |
0.30 |
0.20 |
0.20 |
0.30 |
0.20 |
0.70 |
0.50 |
3.10 |
UM |
0.40 |
0.20 |
0.05 |
0.10 |
0.25 |
0.20 |
0.35 |
0.20 |
1.75 |
LO |
0.07 |
0.04 |
0.01 |
0.02 |
0.04 |
0.04 |
0.07 |
0.04 |
0.33 |
|
|
|
|
|
|
|
|
|
|
Total |
4.39 |
2.26
|
0.57 |
1.24 |
1.88
|
1.79 |
4.34 |
2.24 |
18.71 |
|
|
|
|
|
|
|
|
|
|
%
effort |
23.46 |
12.08 |
3.05 |
6.63 |
10.05 |
9.57 |
23.20 |
11.96 |
100 |
|
|
|
|
|
|
|
|
|
|
|
|
Cust.
Comm. = Customer Communication
Cust. Eval.
= Customer Evaluation
>>
Based on the historical data we obtained, the estimated
effort is approximately 18.71
person – months.
>> The estimated project
cost is RM
4,500 x 18.71 ≈ RM 85,000
|
|
Return
to top |
|
2.2.2 LOC – Based Estimation ( COCOMO Model )
The
following estimates are based on the derivation of using
three - point estimation techniques.
E = (o + 4r + p) / 6
E
= estimate
o = optimistic
estimate
r = realistic
estimate
p = pessimistic
estimate
|
|
Function |
Estimated
LOC |
Login |
100 |
Customer
Details Management |
1000 |
Application
Processing |
900 |
Approved
Loan Management |
550 |
Loan
Account Management |
600 |
Transaction
Processing |
1150 |
Month
– End Interest Calculation |
450 |
Report
Generation |
1400 |
User
Maintenance |
300 |
Logout |
50 |
|
|
Total
Estimated Lines Of Code |
6500 |
|
|
The estimates for LOC are plugged into the COCOMO formula
for effort and duration estimation. The basic COCOMO Model
is used, for which
>> Effort, E = a KLOC
b
>> Duration, D = c E
d
The project is classified as an organic ( simple ) project,
using default values
a = 2.4, b = 1.05, c = 2.5 and d = 0.38.
E = 2.4 (
KLOC ) 1.05
= 2.4 ( 6.5 ) 1.05
≈
17 person – months
D
= 2.5 E 0.38
= 2.5 ( 17 ) 0.38
≈
7.3 months
N = E / D
= 17 / 7.3
≈
2
>>
The
results that we get from the calculations above indicate
that for 2 staff members, it will take 7.3 months to finish
the project. Since we have 4 team members, the project duration
should be shorter. The best – effort estimation for
the project duration
because of the additional members is about 4
months.
>>
Based
on that calculation, the estimated project
cost will be
RM 4,500 x 4 x 4 ≈
RM 72,000
|
Return
to top |
|
2.3 Reconciled Estimate
The following estimates are the final cost, effort and duration
for this project at this point of time.
Estimation
for Effort:
>> Total estimates
for this project range from low of 17
person - month (derived using a LOC based
estimation approved ) to a high level of 18.71
person - month ( derived using the process
based estimation approach )
>> The average estimate
(using 2 approaches) is 17.86
person – month.
Estimation for Duration:
>> From using a process – based estimation approach,
the estimate for is 4.7 months
and from using a LOC – based estimation approach,
the estimates is 4 months.
>> The average estimate
(using 2 approaches) is 4.35
month.
Estimation
for Project Cost:
>> The estimate that we get from the process –
based approach is RM 85,000
and from the LOC – based approach, the estimate that
is calculated is RM 72,000
>> The average estimate ( using 2 approaches ) is
RM 78,500
|
|
Return
to top |
|
2.4 Project Resources
Project
resources needed to develop this system are discussed in
this section.
|
|
2.4.1 People
This
project will require 4 experienced programmers in order
to be completed within the allocated time. Each of the members
should have vast experiences on past projects and all the
team members will have to work in an interrelated network
environment ( ego – less ) where informal meetings
should be held regularly in order to create a more conductive
environment and also to have a more efficient communication
between the team members. Besides that, due to the shortage
of team members, each team member will have to perform multiple
tasks.
Required
Staff:
>> Lead ASP programmer
>> Assistant ASP programmers
>> Documentation / Librarian
>> Manual Designer
>> Graphical Designer
>> Web Designer
>> Beta Testers
|
|
Return
to top |
|
2.4.2 Minimal Hardware Requirements
This
project’s hardware environment will be Intel –
based Pentium with Windows 2000 Server.
>>
4
IBM PC with the following configurations
• P III 600 MHz
• 256 MB SRAM
• 20 GB HD
• Internet Connection
• CD – ROM Writer
|
|
Return
to top |
|
2.4.3 Minimal Software Requirements
The
minimal software needed to develop this system is as below:
>>
Software
• Windows 2000 Server ( 4 licences )
• SQL Server 2000 Standard ( 10 CALs )
• Internet Information Server 5.0 ( IIS )
• Visual Interdev 6.0 ( 4 user licences )
• Microsoft Office 2000 ( 4 licences )
|
|
Return
to top |
|
|
|
All Rights Reserved © Copyright 2003
ESoft Sdn. Bhd.
|