Site hosted by Angelfire.com: Build your free website today!

Access Network Planning and Technologies

4

Planning Access Networks

This section deals with the planning issues involved in the access networks. The accent is more on the traditional network with appropriate mentions of the new technologies. Planning issues of new technologies in the access network would however be taken up in another section If you wish to go back to the introduction page click on the link here

1.0 Introduction

A large part of investment made in telecommunications is made in the subscriber or access part of the network. This investment, in many cases, may exceed fifty percent of the total capital investment made in a local exchange area. With such large investments at stake and increasing subscriber expectations, how does one continue meeting subscriber requirement in an effective manner? In order to continue meeting customers requirements in an effective manner it becomes imperative to properly plan networks based on a sound forecast using a scientific approach.

2.0 Flexible Networks

We saw earlier that the copper based access network may have one or two flexibility points a.k.a the cross connection points(CCP). The first one from the exchange is called the primary CCP or cabinet and the second one, if provided, is called the secondary CCP or pillar. The network therefore gets divided into two or three parts viz., primary, secondary and distribution. In many networks only cabinet exists and therefore we have only two parts of the plant: primary and distribution.

Any pair in the cable from a DP to a cabinet can be connected to any pair of the cable between the cabinets and the exchange. In this way, all smaller pair groups from the DPs (distribution cables) can be combined to form larger pair group to the exchange (primary cable). Distribution areas are smaller(tens of subscribers) and the demand can fluctuate from the forecast by a large percentage. Considering the whole cabinet area, however, the fluctuations largely balance out and considerably smaller number of spare pairs in the primary cable section is necessary.

Some of the advantages of having flexible networks are: sections of the network can be developed independently, making unexpected situations easier to handle. Flexibility obtained by the use of cabinets permits a high cable fill of nearly 90% for the primary cables. Cable fault localization is facilitated by the possibility of disconnection and testing at the cabinet.

Some of the disadvantages of this system are: cabinets are unsuitable for highly humid areas with accompanying risk of low insulation. Frequent handling of a cabinet's jumper field and consequent liability of faults can not be totally eliminated.

Advantages, however, far outweigh the disadvantages.

3.0 General Steps for outside plant planning

The broad activities involved in the outside plant planning are:

  1. The line plant forecast at appropriate level(branch/city/exchange area) shows where circuits will be required for telephone and miscellaneous equipment, both for residential and business tenancies. This forecast is done and reconciled as per the procedure discussed earlier.
  2. Details of the existing plant should be obtained from drawing office, record office and from planning records of the existing network.
  3. Field surveys may be conducted, if required, in one or two stages. In the preliminary survey the planner can get a general idea of the area, existing plant construction difficulties, terrain, trees etc. The detailed survey would give information about surfaces, exact location of plant, duct space, joint positions etc.
  4. Keeping in view the information collected above requirements of physical pairs and/or logical channels (e.g. in case of fibre optic network) is decided at various points of the network. If the initial objective of planning is to produce an overall plan of the area(to be later on subdivided into a number of detailed schemes) then a total of distribution pairs for each cabinet area can be assessed and primary pairs/channels required to feed these pairs would be calculated. If the plan is for an existing area then what we are essentially doing is providing relief to the network. Splitting cabinet areas, providing more cabinets, giving more primary pairs would be the activities involved. For a new area plan appropriate number of cabinets/ONUs, primary cable, distribution cable etc.
  5. An assessment of resources required to carry out the above work is made. This may need to be approved at an appropriate level in the organisation. Budgetry allocations would be made based on these overall calculations.
  6. Detailed schemes for distribution network, primary network and duct & other civil works would be prepared. Transmission and signalling losses are ensured to be within limits.We would see more details of the distribution and primary network planning in the later sections. A detailed estimate comprising stores, manhours, contract work(if required)will all costs calculations is prepared for each scheme.
  7. The schemes may require authorization at appropriate level in the organisation.
  8. Work instructions are prepared for the scheme in a manner in which they would be understandable to the construction staff.

4.0 Economic Planning Periods

When cable is laid it is necessary to provide some spare capacity to meet the future requirements. The number of years for which provision is made in advance is called the planning period. If a cable is provided for a long planning period, the initial cost per pair becomes less but considerable cable capacity remains idle for a long time period and such provision becomes uneconomical. On the other hand, if the cable is provided for too short a planning period, the cost per pair becomes very high and the cable provision again becomes uneconomical. There is an optimum period of planning for provision of cables. The economical planning periods for the primary network is short to medium term while that for distribution network is long term. Generally for bigger systems where the demand/rate of growth is high, it is not practicable to have long planning periods in view of uncertainty in forecast, the high capital cost involved, large scale introduction of fibre in the network and technological advances in the access network. It is therefore becoming increasingly common to plan the primary network for 3 to 5 years and distribution network for a 5-10 year forecast.

 

5.0 Planning Distribution Cable Network


The necessity of a distribution scheme results from the need to
  1. Provide additional pairs to serve new properties or to meet an increased demand in existing tenancies or in business premises.
  2. Develop new areas
  3. Alleviate maintenance problems
  4. Plan for introduction of new technologies

While it may not always be possible to do so, it should be a planning objective to ensure that schemes are planned such that plant is provided in advance so that service can be given on demand. In many cases, information on new development is acquired well in advance and as such the preparation of a scheme to meet the demand should pose few problems.

All or some of the following will be required for preparation of a detailed scheme:

All up to date records should be obtained from the drawing office and in turn the planner should advise the drawing office of any discrepancies found during the survey. Maintenance should be asked for details of any plant which has been giving undue maintenance difficulties so that where possible these can be cleared up in the design of the new scheme. Similarly, external works, should be consulted about any construction difficulties likely to be encountered. In addition information on road works either by Municipalities or other services which may affect the locality should be sought.

5.1 Plant provision policy

The policy when designing relief to an existing distribution area is the overlay principle. The existing network should be disturbed as little as possible except for requests to uplift existing plant which is or likely to cause maintenance or construction problems. Pairs' changeover should be avoided unless it can be established that it would be economic or would be preferable engineering method. Sufficient pairs should always be provided to enable exclusive service to be given to all customers. As with the main cable network, continuous monitoring of the network will indicate which parts need relief. Individual relief requirements will form a series of schemes that will be executed when 'triggered' by demand or when resources are available.

5.2 Planning for new areas

A section would correspond to one DP area and tenancies should be grouped into DP areas such that a standard size cable will meet the 10 year pair requirement calculated in accordance with the pair provision norms. All the sections may not require DPs to begin with and one DP can serve more than one section. As the area develops, more DPs will be opened and subscribers suitably transferred. DP cables may be grouped into larger cables in the course of proceeding back towards the cabinet. Normally all DP pairs are connected to the cross-connection point but the number of through pairs from residential DPs which have flexibility, (e.g. overhead radials), may be reduced to the forecast number of tenancies where this will result in smaller cables towards the cabinet. The overall aim is to achieve a clean layout. Joints with an unequal number of pairs in and out should be avoided wherever possible.

5.3 Planning relief to existing network

Methods of distribution and provision of plant for new development and new estates are fairly straightforward. However, developing and/or providing relief to existing networks creates extra difficulties as a "live" network already exists and proposed improvements or augmentation require to be properly integrated with least disturbance to the existing network.

Where additional pairs have to be provided to meet an increased demand in existing areas, problems are more difficult. We need to answer questions like "How many extra pairs to provide?" Or "Which other DPs should be relieved at the same?" or type and size of DPs to be opened, location of DPs, transfer of DPs from one cabinet to another, diversion of pairs, etc. Many of these do not have such straightforward answers. It is possible, however, to predict the future exhaustion of DPs from an inspection of the spare pairs when considered in relation to the line plant forecast. Absolute accuracy is not so important as slight over-provision can not only be tolerated but also acts as a safety margin.

This calls for good engineering planning. The extreme "cure" for exhausting existing networks would be to completely replace them with new plant and recover the old. This radical solution is unlikely to be adopted except perhaps in areas where the existing network has deteriorated to the extent that there is a very high maintenance cost liability or it will not support new services. Normally such a course of action would be a totally uneconomical

The simplest and most economic way of providing service is by means of overhead distribution and this method should be used wherever it is acceptable and appropriate. However, in some residential areas, the quality of housing and nature of the locality may dictate, apart from Town Planning agreement that an underground distribution system is required. The method of providing service cables and distribution cables to the tenancies concerned is known as under ground radial distribution. The service cables, are laid from the house or villa to the footway and then along the footway to a common point where they are jointed to the distribution cable in a sleeve joint. Radial systems give a good service reliability, are easy to maintain and have an accessible test point inherent in the design.

Multi-story residential and business blocks should be served by underground cable terminated within the building on an internal DP.

6.0 Planning Main Cable Network

The need for a cable scheme is indicated by the anticipated shortage of cable pairs between the exchange MDF and one or more cabinets or direct DPs. When planning relief to the exhausted area, consideration should also be given to relieving any other cabinets on the common cable route where existing plant is insufficient to cater for the planning period which, as mentioned earlier, is 3 to 5 years for the primary cable.

Each relief scheme should be based on a line plant forecast of growth for the area concerned. Confirmation that a forecast is up to date should be obtained before it is used in the design of a scheme.

For this purpose all existing and forecast connections should be considered with an addition for miscellaneous included to give the total forecast connections. The additional pair requirement is then calculated by subtracting the existing pairs from the forecast connections at the end of the third year from completion of the scheme or for the 5 year planning period.

This process is repeated for all subsequent relief schemes so that all unforeseen changes in the forecast growth may be taken into account. Thus each successive relief will be considered as the initial installment of a new relief sequence.

The objective is a clean layout with all conductors connected through at joints, giving full utilization of the plant provided and a simply executed job. Cable should be provided in the longest possible lengths consistent with other considerations. Where joints are unavoidable their positions should be selected having regard to economics and the work location. In some cases economies can be achieved by having parallel cables over a section of route so as to avoid costly enlargement of existing jointing chambers to accommodate extra large joints.

As in the case of planning distribution cables, maintenance staff should be consulted to ascertain whether any plant is giving particular problems so that, if possible, these can be cleared up on the proposed scheme. Schemes must be planned economically but planners should always bear in mind the finished layout and future maintenance. Joints should be accessible and duct-ways not obstructed. Joints in any event are a maintenance liability and their numbers should be kept as low as possible.

New cabinet may be required if the existing cabinet in any area does not have enough primary termination space or distribution termination space as dictated by the planning requirements. In such a situation the existing cabinet area is bifurcated and suitable transfer of the existing DPs is planned.

The location of the cabinet will be at a place where a number of distribution cables of this area meet. Generally the location of the cabinet will be at the beginning of the cabinet area towards the exchange side to avoid any back-feeding of the distribution cable. In this way, the number of cabinets for the exchange area under study as well as their locations are finalised.

Some considerations in locating a cabinet are as follows.

a) The function of the cabinet is to provide flexibility. Unless there are 5 to 6 DPs in a block, a separate cabinet for the block may not be justified instead the DPs can be served from the cabinet in an adjoining block. In such cases, the entire block must be included in adjoining cabinet area.

b) The best point for location of cabinets is on the primary cable route after it enters the cabinet area. Aim would be to reduce back-feeding and the distribution network cost

c) The cabinet area should be so demarcated that no major road crossings are encountered while laying distribution cables to feed the DPs of the area.

d) Primary cables being ducted are safer as compared to the distribution cables which may be directly buried. The distribution cables are the weakest element in the system. Therefore, the distribution cable length from cabinet to the last DP should be the minimum possible keeping in mind the objective of reducing back feeding as well.

e) The cabinet should not be target for any vehicular traffic.

f) It should be away from the electrical cabinets.

g) It should be away from the kerb stone i.e. adjacent and parallel to the wall.

h) It should be so located that even on heavy rainy days the lowest connection strips do not get submerged. For this local enquiries may have to be made to find out maximum flooding level. If a cabinet has to be located in water logged areas then it should be on a suitable foundation.

Normally larger cabinet areas are more economic than smaller ones so the aim should be to plan for these rather than a greater number of smaller areas.

Full regard to safety aspects is essential. Economic considerations should not outweigh the safety of staff, public and plant. Where possible, work in dangerously situated jointing chambers should be avoided. This may mean giving thought to the construction of a new jointing chamber or providing extra joints or even seeking an alternative route.

The site of all proposed work should be surveyed and changes made to initial proposals if necessary. The planner should "think through" the works operations and if appropriate discuss any problems with works staff. If required, the planner should give guidance during the work and be prepared to modify the proposals to suit site conditions.

7.0 Duct Planning

The system of laying cables in pipes laid underground with provision of manholes/ joint boxes at specified distances so that, without resorting to repeated digging, these cables may be operated for rectification of faults or for joining with other cables. Additional cables may be laid subsequently on the same route in near future. Ducts are planned for long term.

 

7.1 Planning Ducts

 

Ducted cable system eliminates all the disadvantages of directly buried cables and gives many more advantages. It acts as a primary protective cover for the cable and minimizes the sheath punctures. The number of interruptions and breakdowns of services are reduced considerably. The life of cable is increased due to reduced handling and better protection.  Unnecessary digging of roads for frequent burial of cables is avoided, consequently there is saving to the company. Unarmoured cables are laid in the duct resulting in 25 to 30% saving in the cost of cables.  Installation of cables becomes easy and quick and expansion programmes can be carried out more economically and quickly. Jointing operations can be done more conveniently. The joints, PTVs, loading coils, PCM repeaters can be conveniently located in the jointing chambers and are accessible for maintenance easily.  Interference with other utility services like water works, electricity authority etc. is also minimized.

While planning ducts appropriate clearance should be given from other installations like gas or water mains, sewers and subways, electric lamp standards, traffic signal posts and other similar plants. Special care should be taken to maintain appropriate clearances from high voltage cables. If a desired separation is not possible a slab of concrete can be made between the two. 

On completion of the duct between any two jointing chambers, or sites thereof, a cylindrical brush and an iron test mandrel shall be passed once through each way to test the duct and remove any foreign matter which may have entered. The size of the test mandrel and brush should be as specified for the particular duct. This will ensure that a minimum of acceptable cabling space is available in each pipe.

 

It may be useful to pressure test all the completed duct sections. Compressed dry air is filled and a desired pressure is created(say 275 millibars). If pressure is retained for sufficient time then there is no leak. In case of leakage the area around the leak shall be thoroughly cleaned with methylated spirits and the leak should be plugged with PVC cement. Retesting should be done after the cement has dried up. It is all the more important to test the sections of ducts leading into exchange buildings. This is to avoid entry of poisonous gases into the cable chambers.

Jointing chambers are constructed on the duct routes to provide access to ducts and also provide space for housing ancillary plant items like regenerators. Jointing chambers can also be provided where severe change in direction is needed in a cable route. This could be at a road junction. Jointing chambers may also be need when a change in formation of duct is desired. These could be constructed in the form of joint-boxes or manholes. They could be made either on the footway or carriageway. They can be made of reinforced concrete or unreinforced concrete. All manholes are designed as carriageway structures and are used in footway and carriageway situations. All manholes will be of reinforced concrete construction. The jointboxes are constructed for carriageway or footway and can be unreinforced or reinforced. If in a situation the standard manhole does not serve the purpose then the dimensions are changed to suit the requirements. 

7.1 Planning Duct space

After determining the cable required as per the planning policies it is necessary to ensure that duct space is available. The existing duct space is said to be ample when space is available for the proposed first and second installments and in this case the initial cable will be provided without further study. The duct space is limited if the space will accommodate a larger size cable than calculated but its provision would preclude any further relief cable being drawn in. Space is just sufficient if the space is available for the proposed initial cable and none remaining. Space is inadequate if it is insufficient space even for the initial cable.

If duct space is ample or just sufficient then the initial cable installment is provided. In case of limited duct space cable can be provided to fill duct space. In case of inadequate space, rearrangement to make space, providing smaller cable, using alternate route and constructing new ducts are the options to be considered. In case of no space new ducts need to be provided.

When a pipe has two or more cable(including the one proposed) then two situations may arise. Assuming that there would be three cables in all and the diameters of these are d, d1 and d2 then:

Case 1: d is the largest cable and sum of diameters of the smaller cables(d1 and d2)

is less than half the diameter of the largest cable then the space taken is only d mm. It is presumed that the smaller cables, d1 and d2, fit into the spaces between the large cable and the walls of the pipe as shown in the diagram

 

                                                     

Fig 1 One large and several smaller cables

Case 2: If sum of the diameters of smaller cables (d1 and d2) is equal to or more than half the diameter of the largest cable (d) then the space required for these cables would be 0.7 x (d1 + d2 +d3)

 

 

 

                                                    

Fig 2 Cables of similar sizes

 

8.0 Transmission and Signalling Limits

With regard to subscribers’ loops, mainly two factors affect the establishment of call and quality of speech. One factor is called as "Signalling Limit" and the second factor is called as "Transmission Loss limit". The former is affected by the direct current (dc) performance of the line while the latter is affected by the alternating current (ac) performance of the line.

The signalling limit relates to calling, dialing or ring trip functions etc. The d.c. loop condition is used to indicate origination of call by a subscriber and d.c. loop interruption pulses are used to indicate dialing in many cases. However for call originating condition, the d.c. loop resistance decides the signalling aspect. Electronic exchanges are capable of accepting loop resistance in the region of 2000 ohms. This limit differs with different exchange equipment. This loop resistance consists of line resistance, transmitter resistance and resistance of the relay in the exchange. The administrations policy may therefore fix a safe limit from exchange to the DP for the purpose of design of the network.

The transmission loss affects the level of the speech. The end to end loss is important to determine the quality of speech from calling subscriber to called subscriber. The end to end section consists of various components such as calling and called subscriber loops, junction networks and long distance network. Different values of transmission losses have been allocated to different sections. The maximum transmission loss limit prescribed for subscriber loop is 8 dB at 1600 Hz. Examples of loss parameters for normally used cables are given below:

For Private automatic Branch Exchanges (PABXs) the set up involves exchange line upto the PABX and extension line from PABX to the subscriber. The PABX and its extensions consumes about 150 ohms and therefore the parameter used for the exchange line should be reduced by this amount. The dB loss for the PABX is about 1dB and planners should keep this in mind while planning the DP serving PABXs.

10.0 Summary

The planner must strives for "the most economical provisioning of plant, to meet service requirements, consistent with sound engineering principles". We will see more aspects of planning of the access network when we read about new technologies.



1. Introduction to telecommunication networks
2. Structure of the access network
3. Subscriber demand and Traffic Forecasting
5. New technologies in the access network

Home
              Top